skip to main content

Bond Updates

 

 



Before, During and After: Updating Our High School

As part of the 2015 community-approved bond, Walter G. O’Connell Copiague High School was renovated and modernized. To see a the completed work, enjoy this edition of Copiague TV.


The Building of Two Schools

As part of the 2015 community-approved bond, Deauville Gardens East and Deauville Gardens West elementary schools were expanded, modernized and renovated. To see a timeline of the work, please enjoy this edition of Copiague TV.


May 2018

 




February 2018

 




January 2018

 




December 28, 2017

 

Below are photos of work occurring throughout the month of December.

 


November 24, 2017

 

Work on the bond is progressing. Below are photos of work occurring throughout the month of November.





October 25, 2017

 

 

Progress continues to be made on the community-approved bond. Here are a few updated photos from work that has occurred the last few weeks. 

 


 


September 21, 2017

 

 

Here are a few photos from the work happening at our buildings this week.

 


August 23, 2017

 

Progress continues to be made on the summer capital work. Concrete pouring for the foundation of the high school addition and Great Neck Road retaining wall has been completed. A new canopy ceiling at Great Neck Road has been installed, the middle school bus loop has been prepared for asphalt paving, and the high school tennis courts have received new concrete curbs and asphalt paving. New terrazzo flooring at the middle school has been installed and installation of the new terrazzo flooring at Deauville Gardens East and Deauville Gardens West is underway.


 


August 16, 2017

 



August 4, 2017

 

Progress continues to be made on the summer bond projects. To date, demolition of the modular building at Deauville Gardens East and West has been completed; renovations to music rooms at Great Neck Road and the middle school are ongoing; and the new turf has been laid out.

August 4, 2017




July 24, 2017

Over the last few weeks, construction crews have been busy preparing our school buildings as part of the community-approved fall 2015 bond. Major items scheduled for completion this summer include the middle school bus loop, secondary athletic fields, and facility renovations at the middle school and Great Neck Road Elementary School. 

Work has also begun at Deauville Gardens East and Deauville Gardens West. The scope of work scheduled for the addition at East and West include demolition of the existing structure/playground, excavation and pouring of the concrete foundation. Inside renovations, such as mechanical and ductwork, electrical wiring and fire alarms, at West and in the central corridor have started. 

 

July 18, 2017

 

July 11, 2017

 

July 5, 2017